Peterhead Roadworks and nearest areas

St Fergus Gas Terminal Entrance on A90 new

Stop/Go Boards Traffic Control near St Fergus Gas Terminal Entrance

St Fergus Gas Terminal
Start Date16 August 2021
End Date16 August 2021
LocationA90 Links Road St Fergus To Greenwellheads Access Road, St Fergus
Description Works:To control vehicle movements between Tower 207 lay down area and A90 (across from M.O.D police/St Fergus Gas Terminal), whilst aluminium trackway panels are uplifted. Stop go traffic required to control vehicle movements between workforce and public on A90. Stop go traffic management in place to facilitate uplift aluminium trackway panels.
Estimated Duration:1 Working Day
Peterhead Road Information

Follow Peterhead.Live on Facebook for get more actual information

Peterhead Repair leak on 28 Queen street

28 Queen street Peterhead Repair leak on main

Peterhead Repair leak

Parking unavailable on one side of the street

Start Date13 August 2021
End Date18 August 2021
Location28 Queen street, Peterhead, AB42 1TS
Description Works:Repair leak on main
Estimated Duration:6 Working Days
Peterhead Road Information

Follow Peterhead.Live on Facebook for get more actual information

Peterhead North Road new roadworks for 2 Days

From 19 August roadworks on Peterhead North Road

Peterhead North Road
Start Date19 August 2021
End Date20 August 2021
LocationOff Network to A90 (A982 North Rd to Jn L Kirktown), Northbound
Description Works:Trial hole investigation
Traffic Management: Portable Traffic Lights
57xzz 2

Follow Peterhead.Live on Facebook for get more actual information

Peterhead Road Information

Kirk street Peterhead new roadworks for 11 Days

Kirk street Peterhead one lane closure

Kirk street Peterhead
Start Date:9 August
End Date:20 August
Promoter:Scottish & Southern Electricity Networks
Location:Kirk Street, Kirktown, Peterhead
Description Works:Replacement of faulty underground diversion box , Replacement via a free standing pillar. Lane closure required to allow excavations on road, Reinstatement lorry to park and work safely and footpath closure will also be required to allow install of new pillar and removal of old equipment
Web site:https://www.ssen.co.uk
Estimated Duration:11 Days
Kirk street Peterhead
Follow Peterhead.Live on Facebook for get more actual information

New Skelton Street Peterhead Closure for 5 Days

Skelton Street Peterhead Closure for 5 Days from 16 June Surface Dressing Works

Skelton Street Peterhead

Roadworks – Road Closure

Start Date:16 August
End Date:21 August
Promoter:Aberdeenshire Council
Location:From Hope Street to Ugie Road, Peterhead
Description Works:Surface Dressing Works
Web site:http://www.aberdeenshire.gov.uk/
Estimated Duration:5 Days

Access will be provided for emergency and vehicles requiring access to properties but may be subject to delay until the road is cleared of construction plant to allow safe passage through the work.