Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

RoadWorks

A90 St Fergus – TTLS


A90 St Fergus Portable Traffic Lights TTLS Southbound

A90 St Fergus TTLS1
«©OpenStreetMap» | A90 StFergus Portable Traffic Lights TTLS Southbound
Start Date:16 November 2026
End Date:24 November 2026
Traffic Management:Portable Traffic Lights (TTLS).
Description:Utility Works
Estimated Duration:9 Days
Location:A90 (A982 North Road to Junction Kirktown) Southbound
A90 St Fergus - TTLS
«©OpenStreetMap» | A90 StFergus Portable Traffic Lights TTLS Southbound
Peterhead_line
A90 StFergus Portable Traffic Lights TTLS Southbound | A90 StFergus Portable Traffic Lights TTLS Southbound

Peterhead.Live on

Peterhead_line

New Road Closure A952 Toll Of Birness

Slip Road Closure A952 Toll Of Birness for ground investigation works

Road Closure A952 Toll Of Birness

Drivers are being warned of a temporary road closure affecting northbound traffic at the Toll of Birness junction.

Start Date:2 November 2026
End Date:6 November 2026
Traffic Management:Road Closure
Description:Ground investigation works
Estimated Duration:5 Days
Location:Slip road connecting the A90 and A952 at the Toll of Birness junction.
Diversion:A90, A950 and A952.

The closure applies to northbound traffic only. Temporary signs will indicate the diversion route.

Drivers are advised to follow the signed diversion and allow extra time for their journeys.

Road Closure A952 Toll Of Birness
Peterhead_line

Peterhead.Live on

Peterhead_line

New A952 road Cortes Junction Closure

Resurfacing works on the A952 near Cortes junction Closure

Resurfacing works on the A952 near Cortes junction Closure
Start Date:7 September 2026
End Date:11 September 2026 (approx. 5 days)
Diversion:A diversion route will be signed for through traffic and buses via the A90 to Peterhead and the A950 to Mintlaw.
Traffic Management:Road Closure
Description:Resurfacing works
Estimated Duration:5 Days
Location:the A952 south of the A90 Cortes junction
Cortes Junction Closure
Credit to Aberdeenshire Council
Cortes Junction Closure 1
Credit to Aberdeenshire Council
Peterhead_line

Peterhead.Live on

Peterhead_line

New 87 Weeks Roadworks Between Peterhead & St Fergus

SSEN – Scottish and Southern Electricity Networks essenial network upgrades between Peterhead & St Fergus up to 87 Weeks Roadworks

87 Weeks Roadworks Between Peterhead & St Fergus
Start Date:30 March 2026
Estimated End Date:November 2027
Location:between Peterhead Power Station and St Fergus Gas erminal
Traffic Management:Portable Traffic Lights
Description:Network Upgrades
Estimated Duration:609 Days
87 Weeks Roadworks Between Peterhead & St Fergus
SSEN – Scottish and Southern Electricity Networks essenial network upgrades between Peterhead & St Fergus up to 609 days Roadworks
Peterhead_line

Peterhead.Live on

Peterhead_line

New A90 Peterhead Road Closure

A90 Peterhead Road Closure A982 North Road to Junction Kirktown

North Road min
Start Date:7 December 2025
End Date:19 December 2025
Diversion:N/B traffic to leave A90 at Howe ‘O’ Buchan Rbt, onto the A950, continue to Mintlaw, then turn right onto the A952. Follow the A952 to re-join the A90 at Cortes Jct, Lonmay.
Traffic Management:Road Closure and TTLS
Description:Drainage Improvements – NB and SB Verges
Estimated Duration:Closure for 13 Days
Location: The road will be closed from before Balmoor Bridge to Lunderton Cottage
Closure Time: from 7:30pm – 6:30am

Sources: www.traffic.gov.scot

Peterhead_line

Peterhead.Live on

Peterhead_line