Peterhead Roadworks and nearest areas

New – Prince Street Reconstruction Works 2 weeks

Footway reconstruction works on Prince Street for two weeks

Prohibition of waiting & one way system

Start Date05 September 2022
End Date18 September 2022
PromoterAberdeenshire Council
LocationPrince Street, from St Peter street to Back Street
Traffic Management:Prohibition of waiting & one way system
Description:Footway reconstruction work
Estimated Duration:For 2 weeks commencing 05 September 2022

Source: www.aberdeenshire.gov.uk

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Between Cortes and Logie Lodge on A90

Roadworks on A90 Logie Lodge To A952 At Cortes, Lonmay, Fraserburgh

Start Date10 August
End Date12 August
LocationA90 U25bat Logie-Lodge To A952 At Cortes, Lonmay, Fraserburgh
Traffic Management:Traffic Restrictions
Description:Massonary Wall DCP Repair
Estimated Duration:3 Working Days

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Road A975 Closure for 5 Days

Road A975 Closure From A90 Junction, Near Longhaven to Cruden Bay

Start Date22 August
End Date26 August
LocationA975 Playhillock Road North To A90 Near Longhaven, Longhaven
Traffic Management:Road Closure
Description:Resurfacing Works
Promoter:Aberdeenshire Council
Diversion:A975 to A90, A90 south, A90 onto slip for B9000, B9000 west to A975, A975 to Main Street, Newburgh, Main Street onto A975, A975 to Aulton Road Cruden Bay, Aulton road onto Bridge Street, Bridge St onto Errolston Road, Errolston Road onto A975 and visa versa

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New Mintlaw Roadworks on road A952

Two High Impact Mintlaw Roadworks Start Next Week

North Street

Start Date Between 10 August – 11 August
LocationFront of Garden Centre, North Street, Mintlaw
Traffic Management:Traffic restrictions
Description:METAL WORK HIGH, RESET AND PATCH AROUND WITH 10MM BITMAC
Estimated Duration:3 Working days

South Street

Start Date Between10 August – 11 August
LocationJunction with Nether Aden Road, South Street, Mintlaw
Traffic Management:Traffic restrictions
Description:Surface breaking up around tobies resulting in potholes. Reset and patch around
Estimated Duration:3 Working days