New – Next week on A90 Between Peterhead and Boddam

Next week between B9108 At Boddam To Invernettie Roundabout Peterhead

Planned roadworks

Start Date11/05/2022
End Date13/05/2022
PromoterScottish Water
Location
A90 B9108 Boddam To Invernettie Roundabout, Peterhead
Traffic Management:Traffic Restrictions
Description Works:REPAIR VALVE
Estimated Duration:3 Working Days

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – A90 Part of Peterhead Bypass Closure

A90 Howe O Buchan Roundabout to Waterside Peterhead Bypass Closure

Road Closure

Start Date01/07/2022 – 19:30
End Date05/7/2022 – 6:30
PromoterTransport Scotland – NE Unit Op Company
Location
A90 A950 At Howe O’ Buchan Roundabout To U43b South Of Waterside, Blackhills, Peterhead
Traffic Management:Road Closure
Description Works:Lining Works, Resurfacing
Estimated Duration:5 Working Days
Diversion Information:Diverted form the A90 Along the A950 to Windmill Road Along to A982/North Road and then on to A90.

Source: www.trafficscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Inverugie Road Closure for 5 Days

Inverugie Road Closure C43b U45b At Smiddyhill Via Inverugie To C5b At Hallmoss

Road Closure

Start Datebetween 25/04/2022 – 03/05/2022
PromoterAberdeenshire Council
Location
C43B U45b At Smiddyhill Via Inverugie To C5b At Hallmoss, Inverugie,
Traffic Management:Road Closure
Description Works:Carriageway Patching works
Estimated Duration:5 Working Days

>>> Another part of C43B closure <<<

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Prunier Drive Closure for 3 Days

Prunier Drive, Coplandhill Closure from Junction with Inverugie Road

Prunier Drive
«©OpenStreetMap» | Prunier Drive, Closure

1 Road Closure

Start Datebetween 20/05/2022 – 23/05/2022
PromoterScottish Water
Location
Junction with Inverugie Road
Traffic Management:Road Closure
Description Works:Manhole cover low or broken
Estimated Duration:3 Working Days
Peterhead_line

2 Road Closure

Start Datebetween 23/05/2022 – 24/05/2022
PromoterScottish Water
Location
Outside No 71 and 79
Traffic Management:Road Closure
Description Works:Manhole covers low and breaking out surround x 3
Estimated Duration:3 Working Days
Peterhead_line

3 Road Closure

Start Datebetween 24/05/2022 – 25/05/2022
PromoterScottish Water
Location
Outside No.29 on carriageway
Traffic Management:Road Closure
Description Works:Manhole cover sunken and breaking up surround
Estimated Duration:3 Working Days
Peterhead_line

4 Road Closure

Start Datebetween 24/05/2022 – 25/05/2022
PromoterScottish Water
Location
Outside No.20
Traffic Management:Road Closure
Description Works:2 Manhole covers low and surround breaking up
Estimated Duration:3 Working Days
Prunier Drive
«©OpenStreetMap» | Prunier Drive, Closure

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

New Road Closure in Peterhead Town Centre for 2 Days

Road Closure in Peterhead Town Centre Erroll Street junction Kirk Street roundabout

Planned roadworks

Expected Start Date Between 28/03/2022 – 05/04/2022
Location
Erroll Street junction Kirk Street roundabout
Traffic Management:Road Closure
Description Works:Safe access to Openreach underground structure for cabling works Off Peak working (09:30-15:30) No Excavtion required
Estimated Duration:2 Working Days