A90 Peterhead Bypass Roadworks

Inspections of Infrastructure Next Week on A90 Peterhead Bypass

Start Date22 August
End Date24 August
LocationA90, A982 At Invernettie Roundabout To U190b At Dales Industrial Estate, Peterhead
Traffic Management:Portable Traffic Light
Description:CCTV of culvert under carriageway.
Promoter:Transport Scotland – NE Unit Op Company

Source: www.roadworksscotland.org

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Prince Street Reconstruction Works 2 weeks

Footway reconstruction works on Prince Street for two weeks

Prohibition of waiting & one way system

Start Date05 September 2022
End Date18 September 2022
PromoterAberdeenshire Council
LocationPrince Street, from St Peter street to Back Street
Traffic Management:Prohibition of waiting & one way system
Description:Footway reconstruction work
Estimated Duration:For 2 weeks commencing 05 September 2022

Source: www.aberdeenshire.gov.uk

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – Harbour Street Peterhead Closure for 2 Days

Harbour Street Peterhead from Bridge Street to Harbour Street Middle of Road at Junction XY

Start Datebetween 26/06/2022 – 28/06/2022
PromoterScottish Water
LocationBRIDGE STREET/HARBOUR STREET MIDDLE OF ROAD AT JUNCTION XY: 413673/ 846039
Traffic Management:Road Closure
Description:Replace Meter
Estimated Duration:3 Working Days
Diversion:Union Street, Seagate, Port Henry Road, Ugie Street, King Street, Kirk Street, Charlotte Street, Bath Street, Lodge Walk, Harbour Street and visa versa

Source: https://www.roadworksscotland.org/

Peterhead_line

Plan Ahead with Peterhead.Live on

Peterhead_line

New – High Impact Works A90 Newton of Sandford

Newton of Sandford A90 B9108 At Boddam To A982 At Invernettie Roundabout

Start Date21/06/2022
PromoterScottish Hydro Electric Power Dis
LocationA90 B9108 At Boddam To A982 At Invernettie Roundabout, Peterhead
Traffic Management:Traffic restrictions
Description:Installation of additional Road Studs.
Estimated Duration:2 Working Days